By Martynas Vaitaitis, Builder & Project Manager at Vayton. Checked 21 November 2026.
Your walls
Ceilings
What you need
| Item | Qty |
|---|
Board layout, face by face
Plasterboard questions
How much plasterboard do I need?
Measure each wall: length times height gives the area of one face. A standard 2400 x 1200 board covers 2.88 m². A new stud wall needs board on both faces, so a 3.6 m by 2.4 m partition takes 6 boards. Walls rarely divide evenly into 1200 mm, which is why the calculator counts from a layout and reuses offcuts.
How many plasterboards for a ceiling?
Ceiling area divided by 2.88 m², plus about 10% because ceiling boards are staggered so the ends don't line up. A 4 m by 3 m ceiling needs 5 boards. Add a ceiling above to get the screws and filler too.
How many studs for a stud wall?
Wall length divided by the stud centres, plus one, plus two for each door or window opening. A 3.6 m wall at 600 mm centres takes 7 studs. Metal walls also need head and floor track; timber walls need plates and noggins.
Why count boards from a layout instead of area?
Boards go up in 1200 mm columns, so a 4 m wall needs four columns even though 4 ÷ 1.2 is 3.3. Dividing area by board size and adding 10% waste undercounts some walls and overcounts others. This calculator lays out each face, picks the shortest stock board (2400, 2700 or 3000 mm) that covers the height in one piece, and only drops a board when an opening covers it completely.
How offcuts are reused
A 4 m partition leaves a 400 mm strip at the end of each face. Cut both strips from one board and you buy one board fewer. The calculator does this across every wall that uses the same board, the way a fixer would on site.
Stud centres: 600 or 400 mm?
600 mm suits 12.5 mm and 15 mm board on most partitions. Use 400 mm behind tiles, for heavy fixings, or where the board maker asks for it. We fix plywood backing between studs wherever a TV, cabinets or a basin will hang.
Why 15 mm on ceilings?
On ceilings fixed to joists we normally use 15 mm board. It sags less between fixings and gives a better base for skimming.
What the price covers
Labour to frame, board and tape, plus the materials listed, at typical London rates checked on . It leaves out skimming (about £15 to £30 per m²), electrics, decorating and anything structural. Small jobs carry a minimum charge because travel and set-up cost the same either way.
Fire and sound walls
Building Regulations set fire and sound performance for whole systems, not single boards. If your wall must meet a rating, follow the board maker's system sheet for stud size, board layers and insulation, and check it with building control.