How much concrete do I need?

Foundations are sized by your structural engineer or building control, not by this calculator. It works out the materials for the size you give it.

How much sand and cement for a screed?

How much mortar for bricks or blocks?

Get it priced Email this to myself

Your sizes go with the enquiry. Our visit to measure is free, with no obligation.

Concrete questions

How much concrete do I need for a shed base?

Multiply length by width by depth in metres. A 3 by 2.4 m base 100 mm deep is 0.72 m³; with 10% for waste, order 0.79 m³. Mixed by hand at 1:4, that is 12 bags of cement and about 1.4 tonnes of ballast, or 72 bags of 25 kg ready-mixed concrete.

How many bags of cement and how much ballast for 1 m³ of concrete?

At 1 part cement to 5 parts ballast, about 13 bags of 25 kg cement and 1.9 tonnes of ballast. Dry materials shrink by about a quarter once mixed with water, so the calculator starts from 1.3 m³ of dry materials for each cubic metre you need. UK guides give 11 to 14 bags and about 2 tonnes for this mix, depending on the ballast.

Which concrete mix should I use?

B&Q's guide gives 1 part cement to 5 parts ballast for light wall foundations and fence posts, 1:4 for shed and garage bases, and 1:3.5 for steps, paving and drives left out in the weather. Foundations for an extension follow the engineer's specification instead.

How many bags of ready-mixed concrete make a cubic metre?

About 91 bags of 25 kg, or 112 bags of 20 kg. Wet concrete weighs around 2.3 to 2.4 tonnes per m³, so a 25 kg bag with its water makes roughly 0.011 m³. The yield is printed on the bag, and it varies by brand.

How much concrete for a fence post?

A hole 300 mm across and 600 mm deep holds about 0.042 m³, less the post. Ten of those take 0.42 m³ before waste. Enter them as post holes above.

Screed questions

How thick should a floor screed be?

Tarmac's technical guide gives at least 40 mm for a screed bonded to the slab, 50 mm unbonded (65 mm with heating pipes in it), and 65 mm floating on insulation (75 mm with heating pipes). Specify a little more than the minimum, because the base is never perfectly level.

What is the mix for a sand and cement screed?

BS 8204-1 gives a nominal 1:4 cement to sharp sand by weight, within 1:3 to 1:4.5. By weight is not the same as by bucket: 25 kg of cement at 1:4 goes with 100 kg of sand.

How long does a screed take to dry?

Tarmac's rule is about one month per 25 mm, and two months per 25 mm for any depth above 50 mm. A 65 mm floating screed takes around 3 months. Cold, damp weather and a wet slab make it longer. Heat the room, not the screed, and test the moisture before laying wood or vinyl.

Mortar questions

How many bricks per m²?

About 60 standard bricks (215 by 102.5 by 65 mm) per m² of half brick wall, and 120 for a one brick wall, with 10 mm joints. A standard 440 by 215 mm block works out at 10 per m².

How much sand and cement do I need for 1,000 bricks?

Travis Perkins gives 120 kg of cement and 0.4 m³ of sand for 1,000 standard bricks at 1:5, which is 5 bags of cement and about 0.65 tonnes of building sand.

What mortar mix should I use?

1:5 or 1:6 cement to building sand suits most walls above the damp course. Use 1:4 below the damp course, for copings and for walls that take the weather. The Mineral Products Association's mortar data sheet sets these out by designation; the sand you use moves the ratio within each range.

Sources

Related

More free tools

All free tools

Free visitOur engineer measures or surveys for free, with no obligation to order.

Price in writingAfter the visit we fix the price in writing before any work starts.

Insured£10m public liability insurance. References on request.

See the workProjects · Houzz · Facebook