Construction daywork sheets: what to record and check before approval

Keep the instruction, daily resource record and pricing check connected. Use a blank daywork record and an unpriced example to make missing information visible.

October 16, 2026

Read the guide ↓

Prepared by Vayton Construction Ltd

Planning graphic for construction daywork: instruction, resources, valuation review.

Original planning overview. Use the actual project requirements.

A construction daywork sheet records the resources used for a defined item of work. To review it usefully, keep three things connected: the instruction, the daily record and the agreed basis for valuing the work.

A description such as “extra work, two people” leaves too much to reconstruct. Record where the work happened, what each person did, which materials and plant were used and the references that let the reviewer check the entry.

Separate the instruction from the resource record

RICS NRM 2, section 2.5.9, describes daywork as valuing work through employee time, materials and plant. It also addresses defining the applicable rates and conditions. The contract and the instruction for your project determine whether that method applies.

Before the relevant work, identify the instruction reference, the person authorised to issue it and the required procedure. Keep the daily resource record linked to that instruction. If the basis or authority is unresolved, label the question clearly and refer it to the appointed contract representative.

RICS's change-control guidance emphasises applying the relevant contract procedure and responsibilities. A record of activity should not be treated as a substitute for that process.

What should a daywork sheet record?

Agree the form and submission route with the project team. This is an original planning checklist you can adapt to the project's requirements.

RecordInformation to enter
IdentityProject, date, unique sheet number, revision and related instruction reference.
Work and locationThe task, room or marked drawing location, and what was completed.
LabourWorker or agreed identifier, trade, task, recorded time and any separately identified interruptions.
MaterialsProduct, unit, quantity used and the relevant delivery or issue reference.
PlantItem, relevant identification, recorded use and the supporting hire or site reference.
Supporting evidenceLinked site diary, marked drawing, delivery record or task photograph where appropriate.
Commercial referencesAgreed rate schedule and revision, applicable additions and the person checking the valuation.
ReviewPrepared by, checked by, dates, queries, corrections and what each acknowledgement confirms.

Keep the account of the work readable without opening a photograph. Supporting evidence should help locate or check an entry. Identify the task and location, and leave out unrelated images.

A blank daily record

Copy the following headings into the agreed project form. Leave rates and decisions blank until the relevant person confirms them.

  • Project / location: __________. Date / sheet number / revision: __________.
  • Instruction reference / issued by / date: __________.
  • Work carried out and drawing reference: __________.
  • Labour: identifier / trade / task / recorded hours: __________.
  • Materials: description / unit / quantity / evidence reference: __________.
  • Plant: item / recorded use / evidence reference: __________.
  • Rate and addition references / pricing queries: __________.
  • Prepared by / reviewed by / dates / comments: __________.

An unpriced example

Say an instructed interior alteration includes an additional small patch repair in Room 2. This is a hypothetical record to show the level of detail, not a completed Vayton job, productivity allowance or agreed charge.

FieldIllustrative entry
ReferenceSheet DW-007, revision 1; instruction SI-014; location Room 2, marked drawing A-102.
WorkForm the additional patch described by SI-014; record its actual extent and finish stage.
LabourOperative A: 2 hours; Operative B: 1 hour. Record their respective tasks and check the time entries.
Materials and plantEnter actual quantities and resource records. Mark items not used as “none”, because a blank is ambiguous.
ValuationRate reference and any permitted additions awaiting the designated review; no price assumed.
QueryConfirm whether the instruction includes final decoration or only the stated patch stage.

In this example the labour total is 3 worker-hours. That total describes recorded time, not the number of people on site for a full day. Use the agreed units when applying any rate.

Check the record and valuation separately

Ask the designated reviewer to resolve unclear descriptions, time entries, quantities or supporting references. Preserve the original entry when making a correction, give the replacement a revision and explain what changed.

Then check the proposed valuation against the project's agreed method: the instruction, applicable resource rates, units, additions and arithmetic. Identify costs already included elsewhere so they are not counted again.

State what any signature or acknowledgement confirms under the agreed procedure. Do not assume that a site record, an instruction and acceptance of a price are the same decision. Submission deadlines, authorised signatories and payment consequences need to be checked against the actual contract.

Keep the change visible in the wider package

Link the checked record to the change register and record any unresolved effect on finishes, access or later trades. Our refurbishment quotation checklist covers the broader scope and change information to keep together.