This planning example is for a vacant flat with the room layout retained and no structural alterations. Use it as a starting work schedule. It is not a completed project, a fixed package or a price, and the existing condition and chosen products would still need checking.
Kitchen
The schedule lists removal of the agreed units, preparation, and installation of the selected kitchen, worktops, splashback and finishes. Appliance installation and service connections are identified separately.
Decide before pricing: the final kitchen plan, who supplies each item, worktop templating and fitting, and whether any services move.
Bathroom
This covers removal, substrate preparation (the surfaces behind the tiles), the specified waterproofing and tiling, sanitaryware installation and finishes. The plumbing, ventilation and electrical scope needs confirming too.
Decide before pricing: fixture positions, product selections, tile sizes and extents, access to existing pipework and who supplies fittings.
Living room and both bedrooms
Each room gets its own quantities for wall and ceiling repairs, decorating, floor finishes, skirting and any agreed storage or joinery.
Decide before pricing: repair versus replacement, paint finishes, floor preparation, retained doors and which electrical alterations need a separate allowance.
Hallway and work routes
This covers the flat’s hallway finishes, thresholds and making good, plus protection to shared routes, permitted delivery times, waste removal and the agreed final clean.
Decide before pricing: lift or stair access, storage, building-management arrangements and who organises any required permissions.
Drawings and product choices come first, then protection and the agreed removal. Once surfaces are exposed, we review the conditions before starting service alterations and preparation. Installation and finishing are then coordinated around product deliveries, drying requirements and specialist visits, with snagging and cleaning before handover.
Write down what happens if opening up reveals extra repairs. Structural work, communal services, windows, specialist surveys and unselected products stay outside the assumed scope until they have been assessed and included in writing.