The Future Homes Standard comes into force in England on 24 March 2027. Its big changes are for newly built homes: heating that cannot run on gas or oil, and solar panels on the roof. If you are extending a house or converting a loft, the insulation and glazing limits you have to meet stay exactly where they are now. We checked this by reading the 2026 edition of Approved Document L, Volume 1, against the 2021 edition it replaces, table by table, on 21 November 2026.
The new rules are officially called the Future Homes and Buildings Standards. They come from S.I. 2026/335, and the government set out how they apply in Circular 01/2026. Many older pages still say "Future Homes Standard 2025". Most of the pages written about it are for housebuilders. This one is for a homeowner in London planning a rear extension, a loft or a garage conversion in 2027.
When does the Future Homes Standard come into force?
On 24 March 2027 for most building work, and on 24 September 2027 for higher-risk buildings such as tall blocks of flats. There is a transition. The new rules do not apply to work on a building where a building notice, an initial notice or a full plans application went in before 24 March 2027, as long as the work on that building starts before 24 March 2028. Each building is judged separately, so on a site of several houses some can fall under the old rules and some under the new.
That second date is why some articles say "from 2028". It is the end of the transition, not the start of the new standard.
What changes for new homes
For a home built from scratch, three things change. The main heating has to use a fuel with a carbon factor of no more than 0.086 kgCO2/kWh, which in practice means a heat pump or a low carbon heat network rather than a gas or oil boiler. A new requirement, called L3, makes rooftop solar panels or another source of renewable electricity part of a new home. And the energy calculation used to show compliance moves to version 10.3 of SAP, alongside the government's new Home Energy Model, which the 2026 edition lists as the other approved method for new homes. None of the three is triggered by extending the house you already live in.
Does the Future Homes Standard apply to extensions?
Yes, an extension built after the start date is built under the 2026 edition. But for an extension, the 2026 edition asks for the same thing as the current rules. The solar panel paragraphs say in terms that they do not apply when a home is extended, and the limits for new walls, roofs, floors and windows in an existing home are copied across unchanged:
| New part of an existing home | Limit in 2021 and in 2026 (W/m²K) |
|---|---|
| Roof | 0.15 |
| Wall | 0.18 |
| Floor | 0.18 |
| Window or roof window | 1.4, or Window Energy Rating band B |
| Rooflight | 2.2 |
| Door, more than 60% glazed | 1.4, or Doorset Energy Rating band C |
| Other external door | 1.4, or Doorset Energy Rating band B |
The figures come from Table 4.2 of the 2021 edition and Table 3.2 of the 2026 edition. The table numbers moved because the document was reorganised. The values did not change.
The heating rule is the same story. If a wet heating system is newly installed or fully replaced, boiler, radiators and pipework together, it has to be sized to run at a flow temperature of no more than 55°C. That rule is already in the 2021 edition. Neither edition stops you replacing a gas boiler in an existing house.
How much glass can an extension have?
The glazing limit is also unchanged. The total area of windows, roof windows, rooflights and doors in the extension should be no more than 25% of the extension's floor area, plus the area of any windows and doors in the old back wall that the extension covers up or removes.
A worked example shows how quickly the allowance goes. Take a rear extension 5 m wide and 4 m deep, which is 20 m² of floor. A quarter of that is 5 m². The extension removes the old back door, 0.9 by 2.1 m, and a kitchen window, 1.2 by 1.2 m, which adds 1.9 m² and 1.4 m². The allowance is about 8.3 m² in total. A bifold door 3.6 m wide and 2.1 m high is 7.6 m², so it fits. Add a rooflight of 1 by 2 m and the total is 9.6 m², which is over.

Going over is allowed, but the extension then has to be shown to perform as well as one that keeps to the limit. The 2026 edition names the two other routes. One is an area-weighted calculation, where better walls and roof make up for the extra glass. The other is a full SAP calculation of the house with the extension. On our jobs those calculations are done by the architect or an outside energy assessor, so if the design has a lot of glass, ask for that check before the drawings are final.
Dry lining an outside wall counts as renovating it
This is the rule that catches people out in a refurbishment, and it has not changed either. Approved Document L lists dry lining the inside face of an outside wall as renovating that wall, in the same list as rendering it or stripping it back to the brick. If more than half of the wall is renovated, the whole wall should be brought up to 0.30 W/m²K. A solid brick wall in a London terrace is nowhere near that, so a plan to replace tired plaster on an outside wall with plasterboard can turn into a plan for insulated plasterboard.
There are limits on how far you have to go. The guidance says it is generally reasonable to lose up to 5% of a room's floor area to the insulation, taking into account how the room is used. If the target is not technically possible, or would not pay back within 15 years, the wall is upgraded as far as is practical instead. Our guide to what dry lining is covers the board types, and the page on internal wall insulation covers the work itself.
Loft and garage conversions
Turning a cold loft or a garage into a room is what the document calls a change to energy status. Any new element, such as a dormer, has to meet the new element limits in the table above. Existing parts that stay, such as the garage floor slab or the old walls, have to be upgraded if they are worse than a threshold, to these improved values:
| Kept part | Upgrade if worse than, to (W/m²K) |
|---|---|
| Roof | 0.35, to 0.16 |
| Wall with cavity insulation | 0.70, to 0.55 |
| Wall insulated inside or out | 0.70, to 0.30 |
| Floor | 0.70, to 0.25 |
These are Table 4.3 in 2021 and Table 3.3 in 2026, again with the same numbers. Our garage conversion floor guide works one of them through with board thicknesses, and the loft conversion guide covers the rest of a loft project.
What to do if you are planning an extension for 2027
Because the extension limits are the same, there is no need to rush your building control application in before 24 March 2027 for the sake of the insulation. The date matters more if your plans include a new dwelling, such as a separate house at the end of a garden, because a new home has to meet the new heating and solar rules unless it is covered by the transition.
On the extensions and loft conversions we build, we submit or manage the building control application ourselves and normally insulate with PIR boards. The energy calculations come from the architect or an outside assessor. Agreeing three things early saves redesign later: the glazing area against the 25% allowance, which outside walls will be dry lined, and whether the heating is being extended or fully replaced.
Planning an extension or loft with us
Send us the drawings if you have them, or the size of the extension and where the glass will go. There is no charge for our engineer's first visit and no obligation after it. We will tell you which parts of Approved Document L your project touches before it is priced. See our house extensions and loft conversions pages, or send us the details.