+44 7346 816064Request a quotation

Deflection head: what it is, who sets the gap and how it is built

November 19, 2026

A deflection head is the top detail of a non-loadbearing partition that lets the floor or roof above move without loading the wall. Who sets the gap, British Gypsum's channel sizes up to 50 mm, what a fire rated head contains, timber walls and what to check before boarding.

November 19, 2026

Read the guide ↓

Prepared by Martynas Vaitaitis, Builder & Project Manager

Drawing of a deflection head in section: a deep channel fixed to the soffit, the stud stopping short inside it to leave a movement gap, with labels for the gap set by the engineer and the 50 mm limit of British Gypsum's parts.

Diagram: a deflection head with the movement gap open. Not to scale.

A deflection head is the detail at the top of a non-loadbearing partition that lets the floor or roof above move without pressing down on the wall. The studs stop short inside a deep channel that is fixed only to the slab or beam overhead, and the gap left above them closes as the floor bends under load. A structural engineer sets how big that gap has to be, and on a fire rated wall the whole head has to match a tested system.

The figures here come from British Gypsum's best practice guide to deflection heads (dated 31 October 2025), its deflection head FAQs and LABC Warranty's technical note on accidental loading of internal walls, all read on 19 November 2026. British Gypsum's details are for its own GypWall metal stud systems. Other makers publish their own, so build to the drawings for the system you are actually using.

Why a partition needs a deflection head

Every floor bends a little under load, and the engineer designs it to an allowed amount. LABC Warranty's example is a heavily loaded timber beam spanning 4 m or more, which may be designed to deflect up to 14 mm, or 0.003 times its span, at the middle. A stud wall built tight to the underside of that beam will end up carrying some of its load.

LABC Warranty lists what can follow. The wall bends, finishes crack, floors creak and the floor above can hog, which means bowing upwards. In a building of several storeys the load can pass down onto the floors below and overstress them. In houses it points to trimmer beams around staircases, often laminated veneer lumber (LVL) or engineered I joists, as the ones that need the most thought. If a newer partition has already cracked along its top, our guides to cracks in a ceiling and cracks in new plaster help work out the cause.

How a deflection head works

Everything above the gap is fixed to the soffit and moves with it. Everything below the gap is fixed to the wall and stays where it is. British Gypsum's head for its GypWall partitions has these parts, numbered as in the drawing:

Section through the top of a metal stud partition: the soffit, FireStrip and dropped soffit strips, a deep flange head channel fixed to the soffit, the stud cut short to leave a movement gap with 20 mm still inside the channel, a zone at the top of the boards with no screws, and cloaking angles over the gap on each face.
Diagram: a deflection head in section, set open for downward movement. Not to scale.
  1. The soffit is the slab, beam, joists or deck above. British Gypsum says that in most cases it needs at least the same fire resistance as the partition.
  2. Gyproc FireStrip, a soft 3 mm intumescent strip, goes on the underside of the soffit. In a fire it swells and seals the small gaps where an uneven soffit meets the flat board strips below it. Those strips, of Gyproc CoreBoard or Glasroc F FireCase, form a dropped soffit that keeps the channel below the top of the wall boards, and the boards have to overlap them by at least 7 mm. Gyproc Sealant goes along every junction with the structure to cut air leaks.
  3. The head channel is a Gypframe Deep Flange channel (DC, with 50 mm flanges) or Extra Deep Flange channel (EDC, with 70 mm flanges). It is fixed through the strips to the soffit at 600 mm centres. British Gypsum says its standard FEC channel cannot take movement in most cases.
  4. The studs are cut short to leave the movement gap, which is the engineer's figure. A head for downward movement goes in fully open and closes at the full deflection. A head for movement both ways goes in at what British Gypsum calls the neutral position, so it can close fully at the most downward movement and open fully at the most upward.
  5. At least 20 mm of every stud has to stay inside the channel at all times, including when the gap is at its widest, to keep the top of the wall stable.
  6. No board screws go into the head channel or the movement zone below it. The top row of fixings goes into a Gypframe GFS1 fixing strap across the studs, or into channel noggings, lower down. British Gypsum says the strap is not needed when the studs are at 300 mm centres.
  7. On a fire rated wall, a cloaking element goes over the gap: two 50 mm wide strips of Glasroc F FireCase fixed to the soffit, or a Gypframe GA4 or GA7 steel angle.

British Gypsum adds that the gaps and parts that open and close must not be filled or blocked with any other material, because that can stop the movement and damage the partition.

Who decides the size of the gap?

British Gypsum puts it on the structural engineer. The engineer works out how far the floor or beam will deflect in normal use and may bring in a fire engineer to say how far it will move in a fire. British Gypsum also points to Approved Document B, Part B3, Section 8 for general guidance on allowing for slab and beam deflection in a fire.

LABC Warranty asks whoever designs the floor to state the deflection allowance, mark which walls can carry load and which cannot, and supply a matching deflection head design before any non-loadbearing walls go up. So the figure should be on a drawing before the studs arrive on site, rather than picked by whoever is building the wall.

On our jobs, when a partition runs up to a concrete slab, we leave the gap the structural engineer gives and check it along the head before any board goes on.

British Gypsum's parts cover up to 50 mm of total movement, for example 50 mm downward or 25 mm each way. For more than that it says a bespoke design with other makers' parts is needed, which is likely to need its own fire test evidence.

Which channel for which gap

For a GypWall Single Frame partition with downward movement, British Gypsum's details choose the channel and the dropped soffit strips by the movement allowance:

Movement allowanceChannel and dropped soffit
1 to 15 mmDC channel, one 19 mm CoreBoard or 20 mm FireCase strip
16 to 25 mmDC channel, two 15 mm FireCase strips
26 to 30 mmDC channel, two 20 mm FireCase strips
31 to 35 mmEDC channel, two 20 mm FireCase strips
36 to 45 mmEDC channel, two 25 mm FireCase strips
46 to 50 mmEDC channel, two 30 mm FireCase strips
Over 50 mmA bespoke design outside British Gypsum's parts

By our reading, the switch at 30 mm fits the 20 mm rule. With the gap fully open, a 50 mm flange still holds 20 mm of stud at 30 mm of movement, and a 70 mm flange does the same at 50 mm. The cloaking grows with the movement too, from two 15 mm FireCase strips up to two 30 mm strips, and the table marks the steel angle as a 30 or 60 minute option. On wider walls with 94 mm or 148 mm channels, the soffit fixings go in two lines, staggered by 300 mm.

Deflection heads on fire rated walls

On a fire rated wall the head is part of the fire separation, and it has to hold at every point of its travel. British Gypsum's fire resistance FAQ says that reaching 30 or 60 minutes "is subject to matching the exact tested system". LABC Warranty says the head should be included in the fire test for the complete wall. Where it is not, an engineer has to assess it to the satisfaction of building control or the fire engineer, and the same goes for firestopping around pipes or cables that pass through near the head.

The top edge of the wall boards must cover the head channel all through the movement, so the channel is never exposed to the fire. The dropped soffit strips keep the channel low enough for that.

Under the older BS 476-22, a wall with a deflection head is tested with the gap set halfway. BS EN 1364-1 does not say where to set it, and British Gypsum treats the gap fully open as the worst case and designs its details for that. BS EN 1364-1 also reads the temperature at 12 or more points on the unexposed face, against at least five under BS 476-22, which is why British Gypsum calls it the harder test. When you compare fire reports for two partitions, check which standard each one used.

Sound through the top of the wall

A gap at the head is a path for sound as well as fire. British Gypsum's alternative head, drawn without the cloaking strips, carries a note warning of a possible loss of around 4 to 5 dB of sound insulation through air leakage. On a wall with a sound rating, keep the sealant and the cloaking in. Our page on acoustic partitions covers the rest of the wall.

Can a timber stud wall have a deflection head?

Not one from British Gypsum. Its FAQ says it cannot offer a way to take head deflection in a non-loadbearing timber frame partition that is practical to build and still keeps the specified fire resistance and sound separation. Its tested deflection heads are for GypWall metal stud systems.

LABC Warranty describes the usual head for each type of wall:

Wall typeTypical head and gap
Metal studsA telescopic head, with a gap of up to 50 mm
Timber studsA metal connector plate with a tapered slot, fixed to the joists above, with a gap of up to 15 mm
BlockworkA sliding steel connector, with compressible material in the joint, with a gap of 50 to 75 mm

So if a timber wall sits under a floor that needs more movement than its connector allows, or the wall has to be fire rated, raise it with the engineer before work starts. A metal stud wall with a tested head is the route British Gypsum offers. For stud sizes and centres, see our guide to stud wall spacing.

What to check before the boards go on

Once the wall is boarded, most of the head is hidden. These checks are worth making while the frame is still open. They draw on British Gypsum's guide and LABC Warranty's note, with a few practical points of our own:

  • The movement figure is on the drawing, with its direction: down only, or up and down.
  • The channel is DC or EDC to suit that figure, fixed to the soffit only, at 600 mm centres through the dropped soffit strips.
  • FireStrip and sealant are in place on the soffit.
  • Measured at a few studs, the gap matches the drawing: fully open for a downward head, at the neutral position for one that moves both ways.
  • At least 20 mm of every stud stays inside the channel with the gap at its widest.
  • No screws go into the channel or the movement zone. The top fixings go into a GFS1 strap or channel noggings.
  • Nothing fills or blocks the gap, such as filler, foam or offcuts.
  • On a fire rated wall, the cloaking is fixed to the soffit and the build matches the tested system.
  • Where the wall meets another partition, the junction follows the maker's detail. British Gypsum warns that these junctions create a problem the trade calls a "mouse hole", and it gives separate details for them.

Photos of the open head, with a tape across the gap, are useful later. Our guide to building control completion records covers what else to keep.

Where deflection heads come up

They come up most on commercial jobs: new partitions under concrete slabs, steel beams and metal decks in offices and shops, where walls are often fire rated too. On an office job the partitions are usually part of the Cat B work, as our guide to Cat A and Cat B fit outs explains. In houses, the walls to watch are new partitions under long timber beams and stair trimmers, as LABC Warranty notes. A partition that stops at a suspended ceiling and fixes to its grid is a different detail, covered in our guide to MF ceilings and bulkheads.

Getting a deflection head built

The first visit from our engineer is free and commits you to nothing. Send us the engineer's movement figure, the fire and sound ratings the wall needs and what sits above it. We then write down the channel, the dropped soffit, the cloaking and the top fixings, and build to the maker's tested detail. See our drylining and ceilings work and office fit outs, or send us the drawings to start.

Chat on WhatsApp